Factors That Affect Cost and Time Using Earned Value In Development Projects

Authors

Titik Nurkaruniati , Budi Witjaksana , Hanie Teki Tjendani

DOI:

10.59888/ajosh.v2i8.309

Published:

2024-05-27

Downloads

Abstract

Effective project management is the key to success in constructing the boarding school of SMA Muhammadiyah 3 Tulangan. Despite facing various challenges such as design changes, inclement weather, and limited workforce resources, the project is monitored using the Earned Value Method. Analysis of BCWS, BCWP, ACWP, SV, CV, SPI, and CPI indicates initial delays and budget overruns, but significant improvement later on. Despite weekly cost variations, the project remains financially manageable. The conclusion shows time delays but cost performance is under control. This underscores the importance of project performance evaluation and the use of the Earned Value Method in construction projects.

Keywords:

boarding school construction; project performance evaluation; earned value method

Author Biographies

Titik Nurkaruniati, Universitas 17 Agustus 1945 Surabaya

Author Origin : Indonesia

Budi Witjaksana, Universitas 17 Agustus 1945 Surabaya

Author Origin : Indonesia

Hanie Teki Tjendani, Universitas 17 Agustus 1945 Surabaya

Author Origin : Indonesia

Downloads

Download data is not yet available.

How to Cite

Factors That Affect Cost and Time Using Earned Value In Development Projects. (2024). Asian Journal of Social and Humanities, 2(8), 1740-1748. https://doi.org/10.59888/ajosh.v2i8.309

Similar Articles

1-10 of 337

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)